PPNA gets major attention in City's 5-year paving plan

Last Autumn, PPNA members voted on "what are the streets within our boundaries, or very nearby streets, that are in the worst condition?" You voted, we compiled, and we sent those results into Councilmember Thao and to the paving department manager to inform the development of the new 2022 5-year plan.  As we mentioned in last January's e-newsletter, we SCORED!  Streets we rated as horrible were all included in the new plan! The City tripled investment from the last 3-year plan, so the picture for us is much rosier.  You can see the full 5-year plan here, but here's a quick snapshot of our streets and the scheduled paving: 23 streets in the 2022 5-year plan plus 6 that were done in the 3-year plan that just ended.

Street- 3yr plan+ Range Plan yr Done Sched Revised Schedule Miles PCI (0 = worst Street type  Notes
Bagshotte Westover to Chelton 3-yr + 5Y   2023 2025 0.22 97 CO Undergrounding coordination
Chelton Dr Haverhill to Chelsea 3-yr + 5Y   2023 2025 0.13 97 CO Undergrounding coordination
Chatsworth Ct All 5-yr   2024 2025 0.09 4 LS  
Chelsea Ct All 5-yr   2024 2025 0.03 5 LS  
Rydal Ct All 5-yr   2024 2025 0.06 5 LS  
Pelham Pl Thackeray to end 5-yr   2024 2025 0.2 8 LS  
Holyrood Mnr All 5-yr   2024 2025 0.05 10 LS  
Mall Ct All 5-yr   2024 2025 0.04 11 LS  
Mountain Blvd Ascot to Kearney 5-yr   2024 2025 0.56 13 LS Kearney to JM Rd done in 3y Plan
Waldeck Ct All 5-yr   2024 2025 0.06 13 LS  
Melville Ln All 5-yr   2024 2025 0.08 14 LS  
Camelford Ct All 5-yr   2024 2025 0.06 15 LS  
Chelsea Dr Chelton to Girvin 5-yr   2024 2027 0.24 19 CO Slide repair must precede paving
Westover Dr Doran to Shelterwod 5-yr   2024 2025 0.31 19 LS  
Westover Dr Shelterwood to Thackeray 5-yr   2024 2025 0.24 19 LS  
Weybridge Ct All 5-yr   2024 2025 0.09 21 LS  
Evergreen Skyline to Moore Dr 5-yr   2024 2025 0.25 23 LS  
Totterdell St All 5-yr   2024 2025 0.08 30 LS  
Skyline Blvd   5-yr   2025 2026 1.94 48 MS  
Darnby Dr Chelton to Carisbrook 5-yr   2026 2027 0.2 76 PM  
Mastlands Dr All 5-yr   2026 2027 0.48 79 PM  
Chelton Elderberry to Exeter 5-yr   2026 2027 0.15 82 PM  
Ascot Ln All 5-yr   2026 2027 0.05 85 PM  
El Caminito All 5-yr   2026 2027 0.13 94 PM  
Castle Park Way All 3-y 3/1/22 2026   0.16 97 PM  
Joaquin Miller Ct All 3-y 5/1/22 2026   0.05 97 PM  
Ascot Mountain to Chelton 3-y 7/1/21 2026   0.41 95 PM  
Camino Lenada All 3-y 7/1/21 2026   0.22 96 PM  
La Cuesta All 3-y 7/1/21            
Thackeray All 3-y 5/1/22            

 

*Street type:  MS=Major Street     LS=Kocal Street      PM=Preventative Mtce     CO=3y carry over)

 

Outside our boundaries, but streets of vital interest to us:  

  • Park Blvd will be paved in 2026 from El Centro (above Glenview village) to Hwy 13, with pothole work in the meantime