PPNA gets major attention in City's 5-year paving plan
Last Autumn, PPNA members voted on "what are the streets within our boundaries, or very nearby streets, that are in the worst condition?" You voted, we compiled, and we sent those results into Councilmember Thao and to the paving department manager to inform the development of the new 2022 5-year plan. As we mentioned in last January's e-newsletter, we SCORED! Streets we rated as horrible were all included in the new plan! The City tripled investment from the last 3-year plan, so the picture for us is much rosier. You can see the full 5-year plan here, but here's a quick snapshot of our streets and the scheduled paving: 23 streets in the 2022 5-year plan plus 6 that were done in the 3-year plan that just ended.
Street- 3yr plan+ |
Range |
Plan yr |
Done |
Sched |
Revised Schedule |
Miles |
PCI (0 = worst |
Street type |
Notes |
Bagshotte |
Westover to Chelton |
3-yr + 5Y |
|
2023 |
2025 |
0.22 |
97 |
CO |
Undergrounding coordination |
Chelton Dr |
Haverhill to Chelsea |
3-yr + 5Y |
|
2023 |
2025 |
0.13 |
97 |
CO |
Undergrounding coordination |
Chatsworth Ct |
All |
5-yr |
|
2024 |
2025 |
0.09 |
4 |
LS |
|
Chelsea Ct |
All |
5-yr |
|
2024 |
2025 |
0.03 |
5 |
LS |
|
Rydal Ct |
All |
5-yr |
|
2024 |
2025 |
0.06 |
5 |
LS |
|
Pelham Pl |
Thackeray to end |
5-yr |
|
2024 |
2025 |
0.2 |
8 |
LS |
|
Holyrood Mnr |
All |
5-yr |
|
2024 |
2025 |
0.05 |
10 |
LS |
|
Mall Ct |
All |
5-yr |
|
2024 |
2025 |
0.04 |
11 |
LS |
|
Mountain Blvd |
Ascot to Kearney |
5-yr |
|
2024 |
2025 |
0.56 |
13 |
LS |
Kearney to JM Rd done in 3y Plan |
Waldeck Ct |
All |
5-yr |
|
2024 |
2025 |
0.06 |
13 |
LS |
|
Melville Ln |
All |
5-yr |
|
2024 |
2025 |
0.08 |
14 |
LS |
|
Camelford Ct |
All |
5-yr |
|
2024 |
2025 |
0.06 |
15 |
LS |
|
Chelsea Dr |
Chelton to Girvin |
5-yr |
|
2024 |
2027 |
0.24 |
19 |
CO |
Slide repair must precede paving |
Westover Dr |
Doran to Shelterwod |
5-yr |
|
2024 |
2025 |
0.31 |
19 |
LS |
|
Westover Dr |
Shelterwood to Thackeray |
5-yr |
|
2024 |
2025 |
0.24 |
19 |
LS |
|
Weybridge Ct |
All |
5-yr |
|
2024 |
2025 |
0.09 |
21 |
LS |
|
Evergreen |
Skyline to Moore Dr |
5-yr |
|
2024 |
2025 |
0.25 |
23 |
LS |
|
Totterdell St |
All |
5-yr |
|
2024 |
2025 |
0.08 |
30 |
LS |
|
Skyline Blvd |
|
5-yr |
|
2025 |
2026 |
1.94 |
48 |
MS |
|
Darnby Dr |
Chelton to Carisbrook |
5-yr |
|
2026 |
2027 |
0.2 |
76 |
PM |
|
Mastlands Dr |
All |
5-yr |
|
2026 |
2027 |
0.48 |
79 |
PM |
|
Chelton |
Elderberry to Exeter |
5-yr |
|
2026 |
2027 |
0.15 |
82 |
PM |
|
Ascot Ln |
All |
5-yr |
|
2026 |
2027 |
0.05 |
85 |
PM |
|
El Caminito |
All |
5-yr |
|
2026 |
2027 |
0.13 |
94 |
PM |
|
Castle Park Way |
All |
3-y |
3/1/22 |
2026 |
|
0.16 |
97 |
PM |
|
Joaquin Miller Ct |
All |
3-y |
5/1/22 |
2026 |
|
0.05 |
97 |
PM |
|
Ascot |
Mountain to Chelton |
3-y |
7/1/21 |
2026 |
|
0.41 |
95 |
PM |
|
Camino Lenada |
All |
3-y |
7/1/21 |
2026 |
|
0.22 |
96 |
PM |
|
La Cuesta |
All |
3-y |
7/1/21 |
|
|
|
|
|
|
Thackeray |
All |
3-y |
5/1/22 |
|
|
|
|
|
|
|
*Street type: MS=Major Street LS=Kocal Street PM=Preventative Mtce CO=3y carry over)
Outside our boundaries, but streets of vital interest to us:
- Park Blvd will be paved in 2026 from El Centro (above Glenview village) to Hwy 13, with pothole work in the meantime